March 23
Next week Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding on Fielder & Hart Cir by Crew #2
Task Rita
Elliot Ct
Finish soding
Task S. Fitz/Wickson Square/Farley Ct
Regrade north ditch on S. Fitz near Wickson Square. Install remaining pipe on Farley Ct
Task Schindler Court
Install pipe, regrade ditches within Court by Crew #1
March 9
Work completed this
week:
Task N.
Fitz/Fielder Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Rita Elliot Ct
Finish installing pipe, regrading, soding, and concrete
paving of driveways
Next week Tasks:
Task N.
Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding on N. Fitzgerald
Task Rita
Elliot Ct
Finish soding
Task
Schindler Court
Start
Date – 3/12/07 – 15 work days
March 2
Work completed this
week:
Task N.
Fitz/Fielder Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Rita Elliot Ct
Percent complete – 20%
Installed
pipe and removed driveways
Next week Tasks:
Task N.
Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding, and concrete paving of driveways|
Task Rita
Elliot Ct
Finish installing pipe, regrading, soding, and concrete
paving of driveways
Task
Schindler Court
Start
Date – 3/5/07 – 15 work days
February 23
Work completed this
week:
Task N.
Fitz/Fielder Cir/Hart Cir/Belnap Ct
Percent complete – 70%
Removed
driveways,
installing pipe, backfilled ditches
Next week Tasks:
Task S.
Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Minor sodding in some areas & floatable fill with some culverts.
Farley Ct & S. Fitz have areas that are to have inlet & piping installed.
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Finish regrading, soding, and concrete paving of driveways
Future Tasks:
Task
Schindler Court
Start
Date – 3/5/07 – 15 work days
February 16
Work completed this
week:
Task S.
Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Regrading, installing pipe, & soding along S. Fitz; Dolye
Circle & Rory Court
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Start Date – 2/19/07 – 10 work days
Percent complete – 20%
Started
regarding,
installing pipe, & soding
Next week Tasks:
Task S.
Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Minor sodding in some areas & floatable fill with some culverts.
Farley Ct & S. Fitz have areas that are to have inlet & piping
installed.
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regarding, installing pipe, & soding
Future Tasks:
Task
Schindler Court
Start Date – 3/5/07 – 15 work days
Percent
complete – 5%
February 9
Work completed this
week:
Task S.
Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Due to water in ditches from last week’s rain, the contractor
has been still regarding cul-de-sacs and still need to place down
sod.
Next week Tasks:
Task S.
Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Percent complete – 90%
Regraded ditches and installed pipe/reset culverts on Farley
Ct & sod all disturbed areas
Future Tasks:
Task N.
Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 2/19/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 3/5/07 – 15 work days
Percent
complete – 5%
February 2
Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey
Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to
be used as a staging area. Once area is not needed, contractor
needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%
Work completed this week:
Task S. Fitz/Farley
Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Due to the rain delays this week, the contractor is still
working in Farley Ct.
Next week Tasks:
Task S. Fitz/Farley
Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 80%
Regraded ditches and installed pipe/reset culverts on Farley Ct
& sod all disturbed areas
Future Tasks:
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%
January 26
Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey
Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to
be used as a staging area. Once area is not needed, contractor
needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%
Work completed this week:
Task S. Fitz/Farley
Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Regraded ditches and installed pipe/reset culverts on S. Fitz,
Rory Ct, & Doyle Cir
Next week Tasks:
Task S. Fitz/Farley
Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 80%
Regraded ditches and installed pipe/reset culverts on Farley Ct
& sod all disturbed areas
Future Tasks:
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%
January 19
Phase 1
(Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be
used as a staging area. Once area is not needed, contractor needs to
sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct
change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%
Work completed this week:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson
Square
Regraded ditches on S. Fitz., Wickson Square & Border Ct
Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson
Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 70%
Regraded ditches and installed pipe/reset culverts on S. Fitz, Rory
Ct, & Doyle Cir; sod all disturbed areas
Future Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%
January 12
Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey
Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to
be used as a staging area. Once area is not needed, contractor
needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%
Work completed this week:
Task Steep
Bank Trace
Finished sodding disturbed areas
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson
Square
Regraded ditches and installed pipe/reset culverts on Wickson
Square & Border Ct
Next week Tasks:
Task S. Fitz/Farley
Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 50%
Regraded ditches and installed pipe/reset culverts on S. Fitz,
Rory Ct, & Doyle Cir; sod all disturbed areas
Future Tasks:
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%
December 22
Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey
Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to
be used as a staging area. Once area is not needed, contractor
needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Work completed this week:
Task Steep
Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 90%
Finished installing box culverts; Still needs to sod disturbed
areas
Next week Tasks:
Contractor to
shut down from 12/22/06 to 1/2/06 for the Holidays
Future week:
Task Schindler
Court
Start Date – 1/2/07
Percent complete – 5%
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson
Square
Revised Schedule (11/7/06) – 19 work days
Percent complete – 2%
December 15
Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey
Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to
be used as a staging area. Once area is not needed, contractor
needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Work completed this week:
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 40%
Started installing box culverts.
Next week Tasks:
Task Steep
Bank Trace
Finish installing box culverts
Contractor to shut down from 12/22/06 to 1/2/06 for the Holidays
Future week:
Task Schindler
Court
Start Date – 1/2/07
Percent complete – 5%
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson
Square
Revised Schedule (11/7/06) – 19 work days
Percent complete – 2%
December 8
Phase 1
(Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be
used as a staging area. Once area is not needed, contractor needs to
sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct
change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Roadway: Wickson Manor
Work completed this week:
Task Wickson Manor
Roadway: Wickson Manor (eastern ditch)
Finish grading and sodded disturbed areas.
Task Schindler Court
Revised Schedule (11/7/06) – 15 work days
Start Date – 12/6/06
Percent complete – 5%
Roadway: S. Fitzgerald
Regrading and resetting culverts along north ditch
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 5%
Started installing box culverts.
Next week Tasks:
Task Schindler Court
Start later in week. Dry Bore 18” w/ steel casing along drainage
easement from Schindler Ct and S. Fitzgerald
Task Steep Bank Trace
Finish installing box culverts
Future week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Start Date – 11/14/06
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Start Date – 12/5/06
Percent complete – 2%
December 3
Phase 1
(Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be
used as a staging area. Once area is not needed, contractor needs to
sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct
change order & 6 rain days)
Work completed this week:
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 95%
Roadway: Wickson Manor
Install 24” RCP from Inlet C-15 to C-16, from Inlet C-16 to C-6,
from MH C-7 to C-8, from MH C-7 to MH Sta 14+41; Install inlets
C-15, & C-16;
Removed and replaced all 24” RCP in the intersection of N.
Fitzgerald & Wickson Manor/Hart Circle; Replace driveways and
roadway; fill in ditch, graded and sodded disturbed areas.
Next week Tasks:
Task Wickson Manor
Roadway: Wickson Manor (eastern ditch)
Finish grading and sodded disturbed areas.
Task Schindler Court
Revised Schedule (11/7/06) – 15 work days
Start Date – 12/6/06
Percent complete – 0%
Dry Bore 18” w/ steel casing along drainage easement from Schindler
Ct and S. Fitzgerald
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – Rescheduled till 12/19/06 (school is out for the
holidays)
Percent complete – 0%
Future week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Start Date – 11/14/06
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Start Date – 12/5/06
Percent complete – 2%
November 17
Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey
Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to
be used as a staging area. Once area is not needed, contractor
needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)
Work completed this week:
Task Wickson
Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 80%
Roadway: Wickson Manor (eastern ditch)
Install 30” RCP from MH at Sta 1+21.87 to Inlet C-6; Installed
24” RCP from inlet C-6 to MH C-7; Installed Inlets C-3, C-4,
C-5, and C-6; Installed MH C-7;
Street cut and Excavated for pipe from Inlet C-6 to Inlet C-16,
for pipe from MH C-7 to MH Sta 14+41, for pipe from MH C-7 to MH
C-8, filled ditch around inlets C-3, C-4, and C-5
Next week Tasks:
Task Wickson
Manor
Roadway: Wickson Manor (eastern ditch)
Install 24” RCP from Inlet C-15 to C-16, from Inlet C-16 to C-6,
from MH C-7 to C-8, from MH C-7 to MH Sta 14+41; Install inlets
C-15, & C-16;
Replace driveways and roadway; fill in ditch, graded and sodded
disturbed areas
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 11/17/06
Percent complete – 0%
Future week:
Task Schindler
Court
Revised Schedule (11/7/06) – 15 work days
Start Date – 11/17/06
Percent complete – 0%
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Start Date – 11/14/06
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson
Square
Revised Schedule (11/7/06) – 19 work days
Start Date – 12/5/06
Percent complete – 2%
November 10
Phase 1
(Contractor – Huff & Mitchell)
Updated schedule is attached.
Work completed this week:
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 40%
Roadway: S. Fitzgerald (southern ditch)
Installed 24” RCP from MH at Sta 21+28.56 to MH at Sta 22+36.25;
Replaced concrete across Wickson Square; Installed 24” RCP and
wingwalls for Wickson Square ditched and southern ditch along S.
Fitzgerald.
Roadway: Wickson Manor (eastern ditch)
Install 30” RCP across S. Fitzgerald, MH at Sta 1+21.87 and
replaced concrete on S. Fitzgerald; Installed 18”x27” pipe along
northern ditch along S. Fitzgerald;
Excavated for pipe from Sta 1+40 to Sta 3+00
Next week Tasks:
Task Wickson Manor
Roadway: S. Fitzgerald
regrade ditch east of Wickson Square and northern ditch.
Roadway: Wickson Manor (eastern ditch)
Install 30” RCP from Sta 1+40 to Sta 3+80; Install inlets C-3,
C-4, C-5, C-6, C-15, & C-16; Install 24” RCP from Sta 3+80 to MH
C-7, Inlet C-15 to inlet C-16 and from inlet C-16 to inlet C-6;
Replace driveways and roadway; fill in ditch, graded and sodded
disturbed areas.
November 3
Phase 1
(Contractor – Huff & Mitchell)
Work completed this week:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 100%
Current actual days – 35 days (this includes 2 days for Farley
Ct change order & 6 rain days)Finish final grading & sodding.
8502 N. Fitz – fill in ditch, add 24” RCP & type A inlet Kelsey
Pass – Remove safety end treatment, add 24” RCP & type A inlet,
and fill in ditch. Farley Ct & S. Fitz – Remove safety end
treatment (SET), add 24” RCP, replace SET, and finish regading
ditch.
Task Wickson
Manor
Revised Schedule (10/4/06) – 13 work days
Start Date – 10/31/06
Percent complete – 15%
Roadway: S. Fitzgerald (southern ditch)
Installed 24” RCP from MH C-1 to MH at Sta 21+28.56; Installed
inlets C-31 & C-32; filled in ditch, graded and sodded disturbed
area.
Next weeks
Tasks:
Task Wickson Manor
Roadway: S. Fitzgerald (southern ditch)
Install 24” RCP across Wickson Square; regrade ditch east of
Wickson Square
Roadway: Wickson Manor (eastern ditch) Install 30” RCP across S.
Fitzgerald and then north along the roadway; install inlets C-3,
C-4, & C-5; fill in ditch, graded and sodded disturbed area.
October 27
Phase 1
(Contractor – Huff & Mitchell)
This week had 2 rain days
Work completed this week:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 95%
Current actual days – 34 days (this includes 2 days for Farley Ct
change order & 6 rain days)Completed final grading, placing of sand
and sod on about 80% of the disturbed areas.
Next week Tasks:
Task S. Fitz/Kelsey Pass
Days needed – 4 days
Finish final grading & sodding. Contractor will finish by Thursday
(10/31/06).
8502 N. Fitz – fill in ditch, add 24” RCP & type A inlet (David
Daniel approved this change order on 10/24/06)
Kelsey Pass – Remove safety end treatment, add 24” RCP & type A
inlet, and fill in ditch. (Tommy Haynes informed contract to
perform)
Farley Ct & S. Fitz – Remove safety end treatment (SET), add 24” RCP,
replace SET, and finish regading ditch. (Tommy Haynes informed
contract to perform)
Task Wickson
Manor
Contractor will be stating this task on Friday (11/3/06)
Revised Schedule (10/4/06) – 13 work days