March 23

Phase 1 (Contractor – Huff & Mitchell)
Work Completed this week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Schindler Court
Installed pipe within the drainage easement between Schindler Ct & South Fitz. Landscape repair & clean up with easement on Saturday.

Next week Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding on Fielder & Hart Cir by Crew #2
Task Rita Elliot Ct
Finish soding
Task S. Fitz/Wickson Square/Farley Ct
Regrade north ditch on S. Fitz near Wickson Square. Install remaining pipe on Farley Ct Task Schindler Court
Install pipe, regrade ditches within Court by Crew #1

March 9

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Task Wickson Manor
Percent complete – 100%
Task Steep Bank Trace
Percent complete – 100%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Percent complete – 95%

Work completed this week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Rita Elliot Ct
Finish installing pipe, regrading, soding, and concrete paving of driveways

Next week Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding on N. Fitzgerald
Task Rita Elliot Ct
Finish soding
Task Schindler Court
Start Date – 3/12/07 – 15 work days

March 2

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Task Wickson Manor
Percent complete – 100%
Task Steep Bank Trace
Percent complete – 100%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Percent complete – 95%

Work completed this week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Rita Elliot Ct
Percent complete – 20%
Installed pipe and removed driveways

Next week Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding, and concrete paving of driveways|
Task Rita Elliot Ct
Finish installing pipe, regrading, soding, and concrete paving of driveways
Task Schindler Court
Start Date – 3/5/07 – 15 work days

February 23

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Task Wickson Manor
Percent complete – 100%
Task Steep Bank Trace
Percent complete – 100%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Percent complete – 95%

Work completed this week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Percent complete – 70%
Removed driveways, installing pipe, backfilled ditches

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Minor sodding in some areas & floatable fill with some culverts. Farley Ct & S. Fitz have areas that
are to have inlet & piping installed.
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding, and concrete paving of driveways

Future Tasks:
Task Schindler Court
Start Date – 3/5/07 – 15 work days

February 16

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Percent complete – 95%

Work completed this week:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Regrading, installing pipe, & soding  along S. Fitz; Dolye Circle & Rory Court
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 2/19/07 – 10 work days
Percent complete – 20%
Started regarding, installing pipe, & soding 

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Minor sodding in some areas & floatable fill with some culverts. Farley Ct & S. Fitz have areas that are to have inlet & piping installed.
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regarding, installing pipe, & soding

Future Tasks:
Task Schindler Court
Start Date – 3/5/07 – 15 work days
Percent complete – 5%

February 9

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:

Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%

Work completed this week:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Due to water in ditches from last week’s rain, the contractor has been still regarding cul-de-sacs and still need to place down sod.

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Percent complete – 90%
Regraded ditches and installed pipe/reset culverts on Farley Ct & sod all disturbed areas

Future Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 2/19/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 3/5/07 – 15 work days
Percent complete – 5%

February 2

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%

Work completed this week:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Due to the rain delays this week, the contractor is still working in Farley Ct.

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 80%
Regraded ditches and installed pipe/reset culverts on Farley Ct & sod all disturbed areas

Future Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%

January 26

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%

Work completed this week:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Regraded ditches and installed pipe/reset culverts on S. Fitz, Rory Ct, & Doyle Cir      

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 80%
Regraded ditches and installed pipe/reset culverts on Farley Ct & sod all disturbed areas

Future Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%

January 19

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area. Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%

Work completed this week:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Regraded ditches on S. Fitz., Wickson Square & Border Ct

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 70%
Regraded ditches and installed pipe/reset culverts on S. Fitz, Rory Ct, & Doyle Cir; sod all disturbed areas

Future Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%

January 12

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 100%

Work completed this week:
Task Steep Bank Trace
Finished sodding disturbed areas
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Regraded ditches and installed pipe/reset culverts on Wickson Square & Border Ct

Next week Tasks:
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Start Date – 1/9/07
Projected Finish Date – 1/19/07
Percent complete – 50%
Regraded ditches and installed pipe/reset culverts on S. Fitz, Rory Ct, & Doyle Cir; sod all disturbed areas

Future Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Start Date – 1/22/07 – 10 work days
Percent complete – 0%
Task Schindler Court
Start Date – 2/5/07 – 15 work days
Percent complete – 5%

December 22

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%

Work completed this week:
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 90%
Finished installing box culverts; Still needs to sod disturbed areas

Next week Tasks:
Contractor to shut down from 12/22/06 to 1/2/06 for the Holidays

Future week:
Task Schindler Court
Start Date – 1/2/07
Percent complete – 5%
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Percent complete – 2%

December 15

Phase 1 (Contractor – Huff & Mitchell) 
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100% 

Work completed this week:
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 40%
Started installing box culverts.    

Next week Tasks:
Task Steep Bank Trace
Finish installing box culverts
Contractor to shut down from 12/22/06 to 1/2/06 for the Holidays

Future week:
Task Schindler Court
Start Date – 1/2/07
Percent complete – 5%
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Percent complete – 2%

December 8

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area. Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 100%
Roadway: Wickson Manor

Work completed this week:
Task Wickson Manor
Roadway: Wickson Manor (eastern ditch)
Finish grading and sodded disturbed areas.
Task Schindler Court
Revised Schedule (11/7/06) – 15 work days
Start Date – 12/6/06
Percent complete – 5%
Roadway: S. Fitzgerald
Regrading and resetting culverts along north ditch
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 12/7/06
Percent complete – 5%
Started installing box culverts.

Next week Tasks:
Task Schindler Court
Start later in week. Dry Bore 18” w/ steel casing along drainage easement from Schindler Ct and S. Fitzgerald
Task Steep Bank Trace
Finish installing box culverts

Future week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Start Date – 11/14/06
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Start Date – 12/5/06
Percent complete – 2%

December 3

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area. Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)

Work completed this week:
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 95%
Roadway: Wickson Manor
Install 24” RCP from Inlet C-15 to C-16, from Inlet C-16 to C-6, from MH C-7 to C-8, from MH C-7 to MH Sta 14+41; Install inlets C-15, & C-16;
Removed and replaced all 24” RCP in the intersection of N. Fitzgerald & Wickson Manor/Hart Circle; Replace driveways and roadway; fill in ditch, graded and sodded disturbed areas.

Next week Tasks:
Task Wickson Manor
Roadway: Wickson Manor (eastern ditch)
Finish grading and sodded disturbed areas.
Task Schindler Court
Revised Schedule (11/7/06) – 15 work days
Start Date – 12/6/06
Percent complete – 0%
Dry Bore 18” w/ steel casing along drainage easement from Schindler Ct and S. Fitzgerald
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – Rescheduled till 12/19/06 (school is out for the holidays)
Percent complete – 0%

Future week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Start Date – 11/14/06
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Start Date – 12/5/06
Percent complete – 2%

November 17

Phase 1 (Contractor – Huff & Mitchell)
Work Completed:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)

Work completed this week:
Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 80%
Roadway: Wickson Manor (eastern ditch)
Install 30” RCP from MH at Sta 1+21.87 to Inlet C-6; Installed 24” RCP from inlet C-6 to MH C-7; Installed Inlets C-3, C-4, C-5, and C-6; Installed MH C-7;
Street cut and Excavated for pipe from Inlet C-6 to Inlet C-16, for pipe from MH C-7 to MH Sta 14+41, for pipe from MH C-7 to MH C-8, filled ditch around inlets C-3, C-4, and C-5  

Next week Tasks:
Task Wickson Manor
Roadway: Wickson Manor (eastern ditch)
Install 24” RCP from Inlet C-15 to C-16, from Inlet C-16 to C-6, from MH C-7 to C-8, from MH C-7 to MH Sta 14+41; Install inlets C-15, & C-16;  
Replace driveways and roadway; fill in ditch, graded and sodded disturbed areas
Task Steep Bank Trace
Revised Schedule (11/7/06) – 4 work days
Start Date – 11/17/06
Percent complete – 0%

Future week:
Task Schindler Court
Revised Schedule (11/7/06) – 15 work days
Start Date – 11/17/06
Percent complete – 0%
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Revised Schedule (11/7/06) – 19 work days
Start Date – 11/14/06
Percent complete – 0%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Revised Schedule (11/7/06) – 19 work days
Start Date – 12/5/06
Percent complete – 2%

 

November 10

Phase 1 (Contractor – Huff & Mitchell)
Updated schedule is attached.

Work completed this week:

Task Wickson Manor
Revised Schedule (11/7/06) – 13 work days
Start Date – 10/31/06
Percent complete – 40%
Roadway: S. Fitzgerald (southern ditch)
Installed 24” RCP from MH at Sta 21+28.56 to MH at Sta 22+36.25; Replaced concrete across Wickson Square; Installed 24” RCP and wingwalls for Wickson Square ditched and southern ditch along S. Fitzgerald.
Roadway: Wickson Manor (eastern ditch)
Install 30” RCP across S. Fitzgerald, MH at Sta 1+21.87 and replaced concrete on S. Fitzgerald; Installed 18”x27” pipe along northern ditch along S. Fitzgerald;
Excavated for pipe from Sta 1+40 to Sta 3+00

Next week Tasks:
Task Wickson Manor
Roadway: S. Fitzgerald
regrade ditch east of Wickson Square and northern ditch.
Roadway: Wickson Manor (eastern ditch)
Install 30” RCP from Sta 1+40 to Sta 3+80; Install inlets C-3, C-4, C-5, C-6, C-15, & C-16; Install 24” RCP from Sta 3+80 to MH C-7, Inlet C-15 to inlet C-16 and from inlet C-16 to inlet C-6; Replace driveways and roadway; fill in ditch, graded and sodded disturbed areas.

 

November 3

Phase 1 (Contractor – Huff & Mitchell)
Work completed this week:

Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 100%
Current actual days – 35 days (this includes 2 days for Farley Ct change order & 6 rain days)Finish final grading & sodding.  8502 N. Fitz – fill in ditch, add 24” RCP & type A inlet  Kelsey Pass – Remove safety end treatment, add 24” RCP & type A inlet, and fill in ditch.  Farley Ct & S. Fitz – Remove safety end treatment (SET), add 24” RCP, replace SET, and finish regading ditch.

Task Wickson Manor
Revised Schedule (10/4/06) – 13 work days
Start Date – 10/31/06
Percent complete – 15%
Roadway: S. Fitzgerald (southern ditch)
Installed 24” RCP from MH C-1 to MH at Sta 21+28.56; Installed inlets C-31 & C-32; filled in ditch, graded and sodded disturbed area.

Next weeks Tasks:
Task Wickson Manor
Roadway: S. Fitzgerald (southern ditch)
Install 24” RCP across Wickson Square; regrade ditch east of Wickson Square
Roadway: Wickson Manor (eastern ditch) Install 30” RCP across S. Fitzgerald and then north along the roadway; install inlets C-3, C-4, & C-5; fill in ditch, graded and sodded disturbed area.

October 27

Phase 1 (Contractor – Huff & Mitchell)
This week had 2 rain days
Work completed this week:
Task S. Fitz/Kelsey Pass
Revised schedule (10/4/06) – 24 work days
Percent complete – 95%
Current actual days – 34 days (this includes 2 days for Farley Ct change order & 6 rain days)Completed final grading, placing of sand and sod on about 80% of the disturbed areas.

Next week Tasks:
Task S. Fitz/Kelsey Pass
Days needed – 4 days
Finish final grading & sodding.  Contractor will finish by Thursday (10/31/06).
8502 N. Fitz – fill in ditch, add 24” RCP & type A inlet (David Daniel approved this change order on 10/24/06)
Kelsey Pass – Remove safety end treatment, add 24” RCP & type A inlet, and fill in ditch.  (Tommy Haynes informed contract to perform)
Farley Ct & S. Fitz – Remove safety end treatment (SET), add 24” RCP, replace SET, and finish regading ditch. (Tommy Haynes informed contract to perform)

Task Wickson Manor
Contractor will be stating this task on Friday (11/3/06)
Revised Schedule (10/4/06) – 13 work days

October 20

Phase 1 –  Construction :
There has been two rain days this week.
S. Fitz.- Contractor was finishing regading of ditches along the east side. 
The contractor has a few driveway repairs to finish.  I have also informed the contractor to sod the areas that are completed.  This should be completed early next week.

 

October 13

Phase 1 –  Construction :
There has been two rain days this week.
S. Fitz.- Inlets A-5, A-6 and A-7 have been installed.  The 30inch RCP connected these inlets has also been installed.  Contractor is ready to install the 24-in RCP that cross S. Fitzgerald from inlet A-6 to inlet A-21. 

The contractor should be finished with this construction task next week.

 

October 5

Phase 1 –  Contractor has updated his work schedule.  See attached PDF.
Construction :
Using the updated schedule, the contractor should be finishing the S. Fitzgerald/Kelsey Pass task.  Incorporated with this task if the change order for Farley Court.

Kelsey Pass – Inlet A-3 was installed.  Pavement has been restored.

S. Fitz.- Pavement at Kelsey Pass has been restored.   

Farley Ct. – Inlets have been installed.  Redesigned court to solve possible safety issue.  Change Order to follow next week.

 

September 28

Phase 1 – Construction :
Appears to be a little behind schedule, however there were a few days of rain.  Contractor updates his schedule monthly and a new schedule is expected early next week.

Kelsey Pass – 36” RCP was installed from inlet A-2 to A-3.  Traffic plates are still over the open street.  Pavement has not been installed.  Inlet A-3 still needs to be installed.

S. Fitz.- 30” RCP was installed from manhole A-17 to A-18. 24” RCP from manhole A-18 to the east and west were installed along with inlet A-19.  Traffic plates are still over the open street.

Pavement has not been installed. 

Farley Ct. – Redesigned court to solve possible safety issue.  Change Order to follow next week.

 

September 22

Phase 1 – Construction :
Kelsey Pass – 36” RCP is installed along the southeast side along with all associated inlets and manholes.
S. Fitz.- 30” RCP is installed along the south side from K. Pass to the other side of Farley Ct. along with all associated inlets and manholes.

Construction appears to be on schedule.

 

September 15

Phase 1 – Construction continues near K Pass on S Fitz 30” next week. Manhole and 1st inlet are set.

September 8

Phase 1 - Contractor mobilized. Actual construction to begin 11th. Construction to start on far west edge of project area; Kelsey pass and then North and South Fitzgerald.

August 31

Phase 1 – All governmental approvals received.  Developer and Pipeline approvals verbal, will follow through to get at least email confirmation.
Contractor mobilizing for start of construction 9/4/06.  Estimated completion 12/4/06.

August 18

Phase 1 - The contractor is doing final cleanup on other job before mobilizing.  He’s just a few days out yet, but doesn’t expect an impact on completion schedule.  With a cooperative effort of several entities, a laydown yard for construction equipment and supply storage has been identified behind a wooded area off of Kelsey.