Percent of Construction Completed as of April 1, 2008
North Fitzgerald Way - 100%

South Fitzgerald Way - 100%

Smithers Lane - 100%

Westall Lane - 100%

North Fitzgerald Court - 100%

South Fitzgerald Court - 100%

Pennington Court - 100%

Shreve Lane - 100%

Gallaher Court - 100%

Steep Bank Trace Court - 95%                                                       
Pending final punch list and corrective action as necessary



Areas Currently Under Construction as of April 1, 2008

Steep Bank Trace

North Caulder Way

Randon Lane

Pennington Lane

O' Connor Lane                                                                                                     
Estimated Time of Completion May 30, 2008



Remaining Areas to Be Constructed as of April 1, 2008
 

Griffin Lane

South Caulder Way

Roarks Passage                                                                                                   
Estimated Time of Completion June 15, 2008



120 Day Contract - January 2, 2008 thru May 2, 2008

Rain Days Adjustment to Date - May 15, 2008 Completion Date

Schedule is Subject to Change

 

 
?>