March 23
Next week Tasks:
Task Dewalt Way/Outfall
Install concrete to driveway
Task North Fitzgerald – Dewalt Way to Oakland Court
Regrade ditches, install pipe
Future Tasks:
Task North Fitzgerald – Dewalt to Belnap
17 work days
March 9
Work completed this week:
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Rita Elliot Ct
Finish installing pipe, regrading, soding, and concrete
paving of driveways
Next week Tasks:
Task N. Fitz/Fielder
Cir/Hart Cir/Belnap Ct
Finish regrading, soding on N. Fitzgerald
Task Rita Elliot Ct
Finish soding
Task Schindler Court
Start Date – 3/12/07 – 15 work days
Task North Fitz –
Oakland Circle to Kenn Court
Finish regarding and sodding along south ditch from Oakland
Court to Oakland Circle
Task South Fitz
Finish regarding, installing pipe and sodding
Task Dewalt Way/Outfall
13 work days
Future Tasks:
Task North
Fitzgerald – Dewalt Way to Oakland Court
12 work days
Task North
Fitzgerald – Dewalt to Belnap
17 work days
March 2
Contractor – Jimerson Underground
Work Completed:
Task Oakland Way
Outfall – 100%
Task S. Fitzgerald near Oakland Way Outfall – 100%
Task Oakland Way – 100%
Task Oakland Circle (West) – 100%
Task Oakland Circle (East) – 100%
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Percent complete – 95%
Finished regraded ditches along Carden Lane.
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish minor sodding disturbed areas
Task North Fitz – Oakland Circle to Kenn Court
Finish minor sodding at Kenn Court..
Task Dewalt
Way/Outfall
13 work days
Future Tasks:
Task South
Fitzgerald
13 work days
Task North
Fitzgerald – Dewalt Way to Oakland Court
12 work days
Task North
Fitzgerald – Dewalt to Belnap
17 work days
February 23
Contractor – Jimerson Underground
Work Completed:
Task Oakland Way
Outfall – 100%
Task S. Fitzgerald near Oakland Way Outfall – 100%
Task Oakland Way – 100%
Task Oakland Circle (West) – 100%
Task Oakland Circle (East) – 100%
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Percent complete – 85%
Regraded ditches and installed pipe/reset culverts along N.
Fitzgerald near Carden Lane and along Carden Lane.
Task North Fitz – Oakland Circle to Kenn Court
Percent complete – 95%
Started Travis Court and Oakland Court regrading ditches and
installed pipe/reset culverts.
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish repaving areas and sodding disturbed areas along N. Fitzgerald and
Carden Lane
Task North Fitz – Oakland Circle to Kenn Court
Finish minor sodding at Kenn Court.
Task Dewalt
Way/Outfall
Start Date – 2/26/07 – 13 work days
Future Tasks:
Task South
Fitzgerald
Start Date – 2/28/07 – 13 work days
Task North
Fitzgerald – Dewalt Way to Oakland Court
Start Date – 3/8/07 – 12 work days
Task North
Fitzgerald – Dewalt to Belnap
Start Date –
3/8/07 – 17 work days
February 16
Contractor – Jimerson Underground
Work Completed:
Task Oakland Way
Outfall
Percent complete – 100%
Task S. Fitzgerald
near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle
(West)
Percent complete – 100%
Task Oakland Circle
(East)
Percent complete – 100%
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Percent complete – 95%
Regraded ditches and installed pipe/reset culverts along N.
Fitzgerald near Carden Lane
Task North Fitz –
Oakland Circle to Kent Court
Start Date – 1/11/07
Percent complete –
70%
Started Travis Court and Oakland Court regrading ditches and
installed pipe/reset culverts.
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish repaving areas and sodding disturbed areas along N. Fitzgerald and
Carden Lane
Task North Fitz – Oakland Circle to Kent Court
Finish repaving areas and sodding disturbed areas along N.
Fitzgerald, Travis Court, and Oakland Court.
Task Dewalt Way/Outfall
Start Date – 2/19/07 – 13 work days
Future Tasks:
Task South
Fitzgerald
Start Date – 2/28/07 – 13 work days
Task North
Fitzgerald – Dewalt Way to Oakland Court
Start Date – 3/8/07 – 12 work days
Task North
Fitzgerald – Dewalt to Belnap
Start Date –
3/8/07 – 17 work days
February 9
Contractor – Jimerson Underground
Work Completed:
Task Oakland Way
Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald
near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle
(West)
Percent complete – 99%
Still needs to sod
disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing
42” RCP; Still needs to sod disturbed areas
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish
Date – 1/19/07
Percent complete – 90%
Regraded ditches and installed pipe/reset culverts along N.
Fitz. And Cul–de–Sac 3
Task North Fitz –
Oakland Circle to Kent Court
Start Date – 1/11/07
Projected Finish
Date – 1/26/07
Percent complete – 20%
Regraded ditches and installed pipe/reset culverts along N.
Fitz. And Kent Court
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regerading ditches and sodding around Cul-de-Sac 3
Task North Fitz – Oakland Circle to Kent Court
Regraded ditches and installed pipe/reset culverts
Future Tasks: (waiting on updated schedule from Contractor)
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz –
Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz –
Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz –
Dewalt to Belnap
Start Date –
2/5/07 – 10 work days
February 2
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way
Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 60%
Due to the rain delays this week, the contractor is currently working on
areas around N. Fitz & Cul-de-sac 2.
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regarding ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts
Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days
January 26
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way
Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 60%
Regraded ditches and installed pipe/reset culverts up to Cul-de-sac 2 on
N. Fitz & Cul-de-sac 2.
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regarding ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts
Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days
January 19
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas
Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 40%
Regraded ditches and installed pipe/reset culverts.
Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regarding ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts
Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days
January 12
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way
Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Work completed this week Tasks:
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas
Next week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 10%
Regraded ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts
Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days
December 22
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way
Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Way
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Work completed this week Tasks:
Task Oakland Circle (East)
Install 42” RCP from Junction box #47 to inlet #45; Install Junction box
#47 & inlet #45
Next week Tasks:
Task Oakland Circle
(East)
Percent complete – 20%
Install 42” RCP from inlet #45 to inlet #43; Install inlets #44, & 43;
Fill in ditches, grade and sod all disturbed areas.
December 15
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way
Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 99%
Still needs to sod disturbed areas
Work completed this week Tasks:
Task Oakland Circle (West)
Installed MH #46; 24” RCP from MH #46 to Junction Box #47; Regraded
ditch around park
Task Oakland Circle (East)
Install 42” RCP from Junction box #47 to inlet #45; Install Junction box
#47 & inlet #45
Next week Tasks:
Task Oakland Way
Percent complete – 85%
Finish area around electrical and gas conduit; Installing MH #49; Still
needs to sod disturbed areas
Task Oakland Circle (West)
Percent complete – 85%
Install 30” RCP from MH #35 to Inlet #36; Still needs to sod disturbed
areas
Task Oakland Circle (East)
Percent complete – 20%
Install 42” RCP from inlet #45 to inlet #43; Install inlets #44, & 43;
Fill in ditches, grade and sod all disturbed areas.
December 8
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas
Work completed this week Tasks:
Task S. Fitzgerald near Oakland Way Outfall
Regraded both north and south ditches to the west and east of the Outfall.
Task Oakland Way
Installed 48” RCP from MH #52 to MH #47; Fill in ditches
Task Oakland Circle (West)
Install 30” RCP from inlet #37 to #39; Fill in ditches
Next week Tasks:
Task Oakland Way
Finish area around electrical and gas conduit. Grade and sod all disturbed
areas.
Task Oakland Circle (West)
Install 30” RCP from MH 35 to inlet #36; Inlet #36; Fill in ditches, grade and
sod all disturbed areas.
Task Oakland Circle (East)
Install 42” RCP from Junction box #47 to inlet #43; Install Junction box #47,
inlets #45, 44, & 43; Fill in ditches, grade and sod all disturbed areas.
December 3
Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas
Work completed this week Tasks:
Task Oakland Way
Installed 48” RCP from Junction Box to MH #52; Trenching for installation of 48”
RCP along eastern ditch
Task Oakland Circle (West)
Trench for 30” RCP from inlet #37 to #38
Next week Tasks:
Task Oakland Way
Installed 48” RCP from MH #52 to MH #47; Fill in ditches, grade and sod all
disturbed areas.
Task Oakland Circle (West)
Install 30” RCP from inlet #37 to #39; Fill in ditches, grade and sod all
disturbed areas.
November 17
Phase 2 (Contractor – Jimerson Underground)
Work completed this week Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 40%
Installed MH OW-2 and MH OW-3; 48” RCP between manhole and junction box
OW-1
Next week Tasks:
Task Oalkand Way
Outfall
Install junction boxes OW-1 & 55; Install 42” RCP between junction boxes
and replaced concrete on S. Fitzgerald; graded and sodded disturbed
areas.
November 10
Phase 2 (Contractor –
Jimerson Underground)
Work completed this week Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 5%
Installed 48” CMP from outfall to 5 feet of existing wall; sawcut S.
Fitzgerald for removal.
Next week Tasks:
Task Oalkand Way Outfall
Install Man holes OW-2 & 3, junction boxes OW-1 & 55; 48” RCP between
manhole and junction box OW-1; Install 42” RCP between junction boxes
and replaced concrete on S. Fitzgerald; graded and sodded disturbed
areas.
November 3
Phase 2 (Contractor
– Jimerson Underground)
Jimerson was given the door hangers this week for this phase.
Jimerson did not start this week. I have already informed him to
keeping to his schedule. He plans to be out there Monday (11/6/06)
Next weeks Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 0%
October 27
Phase 2 (Contractor –
Jimerson Underground)
Attached is a copy of his schedule.
Next weeks Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 10/31/06
Percent complete – 0%