March 23

Contractor – Jimerson Ungerground
Work Completed this week:
Task North Fitz – Oakland Circle to Kenn Court
Percent complete – 100%
Finished fixing curbing
Task Dewalt Way/Outfall
Installed pipe and inlets, regarded disturbed areas

Next week Tasks:
Task Dewalt Way/Outfall
Install concrete to driveway
Task North Fitzgerald – Dewalt Way to Oakland Court
Regrade ditches, install pipe

Future Tasks:
Task North Fitzgerald – Dewalt to Belnap
17 work days

March 9

Contractor – Huff & Mitchell
Work Completed:
Task S. Fitz/Kelsey Pass
Percent complete – 99% (Tommy Haynes has allowed Kelsey pass to be used as a staging area.  Once area is not needed, contractor needs to sod area)
Task Wickson Manor
Percent complete – 100% 
Task Steep Bank Trace
Percent complete – 100%
Task S. Fitz/Farley Ct/Doyle Cir/Rory Ct/Border Ct/Wickson Square
Percent complete – 95%

Work completed this week:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Concrete paving of driveways were installed.
Task Rita Elliot Ct
Finish installing pipe, regrading, soding, and concrete paving of driveways

Next week Tasks:
Task N. Fitz/Fielder Cir/Hart Cir/Belnap Ct
Finish regrading, soding on N. Fitzgerald
Task Rita Elliot Ct
Finish soding
Task Schindler Court
Start Date – 3/12/07 – 15 work days
Task North Fitz – Oakland Circle to Kenn Court
Finish regarding and sodding along south ditch from Oakland Court to Oakland Circle
Task South Fitz
Finish regarding, installing pipe and sodding
Task Dewalt Way/Outfall
13 work days

Future Tasks:
Task North Fitzgerald – Dewalt Way to Oakland Court
12 work days
Task North Fitzgerald – Dewalt to Belnap
17 work days

March 2

Contractor – Jimerson Underground
Work Completed:
Task Oakland Way Outfall – 100%
Task S. Fitzgerald near Oakland Way Outfall – 100%
Task Oakland Way – 100%
Task Oakland Circle (West) – 100%
Task Oakland Circle (East) – 100%

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Percent complete – 95%
Finished regraded ditches along Carden Lane.

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish minor sodding disturbed areas
Task North Fitz – Oakland Circle to Kenn Court
Finish minor sodding at Kenn Court..
Task Dewalt Way/Outfall
13 work days

Future Tasks:
Task South Fitzgerald
13 work days
Task North Fitzgerald – Dewalt Way to Oakland Court
12 work days
Task North Fitzgerald – Dewalt to Belnap
17 work days

February 23

Contractor – Jimerson Underground
Work Completed:
Task Oakland Way Outfall – 100%
Task S. Fitzgerald near Oakland Way Outfall – 100%
Task Oakland Way – 100%
Task Oakland Circle (West) – 100%
Task Oakland Circle (East) – 100%

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Percent complete – 85%
Regraded ditches and installed pipe/reset culverts along N. Fitzgerald near Carden Lane and along Carden Lane.
Task North Fitz – Oakland Circle to Kenn Court
Percent complete – 95%
Started Travis Court and Oakland Court regrading ditches and installed pipe/reset culverts.

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish repaving areas and sodding disturbed areas along N. Fitzgerald and Carden Lane
Task North Fitz – Oakland Circle to Kenn Court
Finish minor sodding at Kenn Court.
Task Dewalt Way/Outfall
Start Date – 2/26/07 – 13 work days

Future Tasks:
Task South Fitzgerald
Start Date – 2/28/07 – 13 work days
Task North Fitzgerald – Dewalt Way to Oakland Court
Start Date – 3/8/07 – 12 work days
Task North Fitzgerald – Dewalt to Belnap
Start Date – 3/8/07 – 17 work days

February 16

Contractor – Jimerson Underground
Work Completed:
Task Oakland Way Outfall
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 100%
Task Oakland Circle (East)
Percent complete – 100%

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Percent complete – 95%
Regraded ditches and installed pipe/reset culverts along N. Fitzgerald near Carden Lane
Task North Fitz – Oakland Circle to Kent Court
Start Date – 1/11/07
Percent complete – 70%
Started Travis Court and Oakland Court regrading ditches and installed pipe/reset culverts.

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish repaving areas and sodding disturbed areas along N. Fitzgerald and Carden Lane
Task North Fitz – Oakland Circle to Kent Court
Finish repaving areas and sodding disturbed areas along N. Fitzgerald, Travis Court, and Oakland Court.
Task Dewalt Way/Outfall
Start Date – 2/19/07 – 13 work days

Future Tasks:
Task South Fitzgerald
Start Date – 2/28/07 – 13 work days
Task North Fitzgerald – Dewalt Way to Oakland Court
Start Date – 3/8/07 – 12 work days
Task North Fitzgerald – Dewalt to Belnap
Start Date – 3/8/07 – 17 work days

February 9

Contractor – Jimerson Underground
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 90%
Regraded ditches and installed pipe/reset culverts along N. Fitz. And Cul–de–Sac 3
Task North Fitz – Oakland Circle to Kent Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 20%
Regraded ditches and installed pipe/reset culverts along N. Fitz. And Kent Court

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regerading ditches and sodding around Cul-de-Sac 3
Task North Fitz – Oakland Circle to Kent Court
Regraded ditches and installed pipe/reset culverts

Future Tasks: (waiting on updated schedule from Contractor)
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days

February 2

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 60%
Due to the rain delays this week, the contractor is currently working on areas around N. Fitz & Cul-de-sac 2.

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regarding ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts

Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days

January 26

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 60%
Regraded ditches and installed pipe/reset culverts up to Cul-de-sac 2 on N. Fitz & Cul-de-sac 2.

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regarding ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts
 

Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days

January 19

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas

Work completed this week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 40%
Regraded ditches and installed pipe/reset culverts.

Next week Tasks:
Task North Fitz – Oakland Circle to East
Finish regarding ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts

Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days

January 12

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 100%
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 100%
Task Oakland Way
Percent complete – 100%
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas

Work completed this week Tasks:
Task Oakland Circle (East)
Percent complete – 99%
Finished installing 42” RCP; Still needs to sod disturbed areas

Next week Tasks:
Task North Fitz – Oakland Circle to East
Start Date – 1/11/07
Projected Finish Date – 1/19/07
Percent complete – 10%
Regraded ditches and installed pipe/reset culverts.
Task North Fitz – Oakland Circle to Kenn Court
Start Date – 1/11/07
Projected Finish Date – 1/26/07
Percent complete – 5%
Regraded ditches and installed pipe/reset culverts

Future Tasks:
Task Dewalt Way
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to East
Start Date – 1/22/07 – 10 work days
Task South Fitz – Dewalt Way to West
Start Date – 1/29/07 – 15 work days
Task North Fitz – Dewalt to Belnap
Start Date – 2/5/07 – 10 work days

December 22

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Way
Percent complete – 99%
Still needs to sod disturbed areas
Task Oakland Circle (West)
Percent complete – 99%
Still needs to sod disturbed areas

Work completed this week Tasks:
Task Oakland Circle (East)
Install 42” RCP from Junction box #47 to inlet #45; Install Junction box #47 & inlet #45

Next week Tasks:
Task Oakland Circle (East)
Percent complete – 20%
Install 42” RCP from inlet #45 to inlet #43; Install inlets #44, & 43; Fill in ditches, grade and sod all disturbed areas.

December 15

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas
Task S. Fitzgerald near Oakland Way Outfall
Percent complete – 99%
Still needs to sod disturbed areas

Work completed this week Tasks:
Task Oakland Circle (West)
Installed MH #46; 24” RCP from MH #46 to Junction Box #47; Regraded ditch around park
Task Oakland Circle (East)
Install 42” RCP from Junction box #47 to inlet #45; Install Junction box #47 & inlet #45

Next week Tasks:
Task Oakland Way
Percent complete – 85%
Finish area around electrical and gas conduit; Installing MH #49; Still needs to sod disturbed areas
Task Oakland Circle (West)
Percent complete – 85%
Install 30” RCP from MH #35 to Inlet #36; Still needs to sod disturbed areas
Task Oakland Circle (East)
Percent complete – 20%
Install 42” RCP from inlet #45 to inlet #43; Install inlets #44, & 43; Fill in ditches, grade and sod all disturbed areas.

December 8

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas

Work completed this week Tasks:
Task S. Fitzgerald near Oakland Way Outfall
Regraded both north and south ditches to the west and east of the Outfall.
Task Oakland Way
Installed 48” RCP from MH #52 to MH #47; Fill in ditches
Task Oakland Circle (West)
Install 30” RCP from inlet #37 to #39; Fill in ditches

Next week Tasks:
Task Oakland Way
Finish area around electrical and gas conduit. Grade and sod all disturbed areas.
Task Oakland Circle (West)
Install 30” RCP from MH 35 to inlet #36; Inlet #36; Fill in ditches, grade and sod all disturbed areas.
Task Oakland Circle (East)
Install 42” RCP from Junction box #47 to inlet #43; Install Junction box #47, inlets #45, 44, & 43; Fill in ditches, grade and sod all disturbed areas.

December 3

Phase 2 (Contractor – Jimerson Underground)
Work Completed:
Task Oakland Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 99%
Still needs to sod disturbed areas

Work completed this week Tasks:
Task Oakland Way
Installed 48” RCP from Junction Box to MH #52; Trenching for installation of 48” RCP along eastern ditch
Task Oakland Circle (West)
Trench for 30” RCP from inlet #37 to #38

Next week Tasks:
Task Oakland Way
Installed 48” RCP from MH #52 to MH #47; Fill in ditches, grade and sod all disturbed areas.
Task Oakland Circle (West)
Install 30” RCP from inlet #37 to #39; Fill in ditches, grade and sod all disturbed areas.

November 17

Phase 2 (Contractor – Jimerson Underground)
Work completed this week Tasks
:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 40%
Installed MH OW-2  and MH OW-3; 48” RCP between manhole and junction box OW-1

Next week Tasks:
Task Oalkand Way Outfall
Install junction boxes OW-1 & 55; Install 42” RCP between junction boxes and replaced concrete on S. Fitzgerald; graded and sodded disturbed areas.

November 10

Phase 2 (Contractor – Jimerson Underground)
Work completed this week Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 5%
Installed 48” CMP from outfall to 5 feet of existing wall; sawcut S. Fitzgerald for removal.

Next week Tasks:

Task Oalkand Way Outfall
Install Man holes OW-2 & 3, junction boxes OW-1 & 55; 48” RCP between manhole and junction box OW-1; Install 42” RCP between junction boxes and replaced concrete on S. Fitzgerald; graded and sodded disturbed areas.

November 3

Phase 2 (Contractor – Jimerson Underground)
Jimerson was given the door hangers this week for this phase.
Jimerson did not start this week.  I have already informed him to keeping to his schedule.  He plans to be out there Monday (11/6/06)

Next weeks Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 11/06/06
Percent complete – 0%

October 27

Phase 2 (Contractor – Jimerson Underground)
Attached is a copy of his schedule.
Next weeks Tasks:
Task Oalkand Way Outfall
Per Schedule (10/26/06) – 5 days
Start Date – 10/31/06
Percent complete – 0%